Fire Suppression Upgrade Camp Billy Machen

Fed Con/South Bay Joint Venture is tasked to provide all personnel, equipment, tools, materials, technical supervision and other items and services necessary to replace fire pump, electric motor, fire pump motor control, and leaking underground fire suppression line.

Fire Pump House Building 6004
Demolition:
(a) Contractor will remove existing fire pumps and electric motor.
(b) Contractor will remove the 10 inch double check backflow preventer.
(c) Contractor will remove existing fire pump motor control.
(d) Contractors will removes all doors and door frames for building.
(e) Contractor will remove chlorine injection system.

Underground water line.
Demolition:
(f) Contractor will remove associated piping for south side underground fire suppression water line.

Fire Pump House Building 6004
Installation:
a) Contractor will install two new fire pump s and electric motors. Fire pumps shall be like in kind replacement..
b) Contractors will install two new fire pump motor control units for fire pumps.
c) Contractor will install new metal doors and frames for building. Doors will be weather sealed.
d) Contractor will install wall separating electric controls for fire pump and chlorine system from pumps.
e) Contractor will insulate room with electric controls.
f) Contractor will install A/C unit for room with electric controls.
g) Contractor will install a chlorine tablet system for drinking water.
h) Contractor will install exhaust fan. Switch for exhaust fan will be a three way switch, one switch to be located outside new doors and inside room. Exhaust fan will be rated to use for exposure to chorine gas.

Underground water line.
Installation:
i) Contractor will install new10in underground fire suppression water line.
j) Contractor will add four water shut off vales for piping.

Tank 6005
Installation:
k) Contractor will install new 4 in water line from Bldg 6004 fire pumps to Water Tank 6005. Water line will be circulating water from fire pumps back to water storage tank.
l) Contractor will install new 4in Cla-Val on water fill line. Cla-Val will be set up for automatic filling operations for the water tank. Cla-Val will determine filling need by
water pressure or elevation.

 