Repair Indicator Valve at Building 1330 HomeRepair Indicator Valve at Building 1330

Repair Indicator Valve at Building 1330

Federal Construction Group replaced the post indicator valve at building 1330 by demolishing and replace the existing post indicator valve with a 6″ backflow prevention device and 4″ isolation valve complete and ready for use.  We provided traffic control and trench safety precautions as required for the duration of the project.  Excavated and exposed then demolished the existing post indicator valve and limited piping.  We modified the existing piping and brought the line above ground with a 6″ isolation valve.  We installed a 6″ reduced pressure backflow prevention device, installed a reducing fitting on the outlet side of the BFP and reconnected to the existing water line.  We also installed a lock and chain on the valve assembly.  We installed/poured a concrete slab in place with piping support and replaced any damaged grass.