Replace Fire Pump and Install Backflow Preventer at Bldg. 109 HomeReplace Fire Pump and Install Backflow Preventer at Bldg. 109

Replace Fire Pump and Install Backflow Preventer at Bldg. 109

Federal Construction Group, Inc. is tasked to provide all personnel, equipment, tools, materials, technical supervision and other items and services necessary to perform: inspection, abatement, installation and repair to all items within this SOW.

Demolition Plan

  1. Remove fire pump (x2) from fire pumps room and dispose of offsite.
  2. Remove associated piping for fire pumps.
  3. Remove one 36in wide door and concrete walling, door located on south side of pump room.
  4. Remove pump controller if new pumps are not compatible.
  5. Remove PIV and asphalt for install of BFP.

Repair/Replacement.

  1. Install new fire pumps, new fire pumps will meet requirements for gpm, flow psi for hanger design system.
  2. Install new fire pump rater piping associated with install of new fire pump.
  3. Install new fire rated backflow preventer on main supply line for fire suppression water line.
  4. Install new double doors on south side of fire pump room. Doors are for removal and install of new equipment. Paint and texture concrete walling to match existing paint.

 