Correct Erosion Problem at Building 41409 HomeCorrect Erosion Problem at Building 41409

Federal Construction Group performed slope erosion repairs and prevention at building 41409 by removing existing chain link fencing and steel sheeting surrounding oil water separator and demolishing the abandoned 5000 gallon pre-cast concrete oil water separator.  The demoliton included three (3) concrete lids, 12″ PVC storm drain pipe and existing cleanout vault and associated piping.  Saw cut and removed PCC curb, AC road and PCC cross gutter for installation of new storm water pipe.

We installed new curb extension on the south side of existing inlets.  Excavated, placed and poured a 4″ PCC trench/slab and installed new fence around PCC trench/slab with same  type of material as existing fence.  Installed curb extension/cross section on the north side of existing inlets along with an emergency spillway, cross section PCC curb on two sides of the spillway.  The PCC spillway and curb have #3 steel reinforcement horizontal and vertically placed to the PCC swale at toe of slope.  We excavated a trench for the installation of the new Class IV 18″ RCP storm drain pipe.  The new RCP pipe extended from the most westerly existing grated inlet ot the grated inlet on El Camino Real and Nelson Street intersection, approximately 464 lenial feet.  Placed and compacted Class B bedding material in trench per manufactures recommendation and installed one manhole on new drain line.  We backfilled and compacted the trench to 95% maximum density.  Formed and poured PCC curb and cross gutter to same dimensions as existing, to include reinforcing, where new drain pipe was installed.  PCC cross gutter was 7″ thick.  Patched asphalt roadway to same thickness as existing, where new drain pipe was installed.  All irrigation lines and sprinkler heads removed for drain pipe installation were repaired as needed.  A 12″ x 12″ inlet box was installed with grate, over 4′ drain line at end of the concrete swale at toe slope.  We graded the existing slope from 1′ offset from the fence line at top of slope and placed jute netting, and hydro-seed graded bank areas.  Installed 2 new  fence posts, barb arms, barb wire and chin link fabric and installed a filter insert suitable for oils and metals in the primary grated inlet box.

DSCN0489 DSCN0490 DSCN0497 DSCN0496 DSCN0494 DSCN0492 DSCN0491 DSCN0502 DSCN0507 DSCN0509 DSCN0511 DSCN0517 DSCN0519 DSCN0520 DSCN0523 DSCN0529 DSCN0531 DSCN0540 DSCN0539 DSCN0538 DSCN0534 DSCN0532 DSCN0542 DSCN0545 DSCN0547 DSCN0552 DSCN0553 DSCN0565 DSCN0562 DSCN0560 DSCN0559 DSCN0556 DSCN0566 DSCN0567 DSCN0568 DSCN0569 DSCN0570 DSCN0571 DSCN0575 DSCN0576 DSCN0577 DSCN0578 DSCN0585 DSCN0583 DSCN0582 DSCN0581 DSCN0579 DSCN0588 DSCN0589 DSCN0604 DSCN0605 DSCN0609 DSCN0614 DSCN0613 DSCN0612 DSCN0611 DSCN0610 DSCN0617 DSCN0621 DSCN0623 DSCN0624 DSCN0625 DSCN0631 DSCN0630 DSCN0628 DSCN0627 DSCN0626 DSCN0632 DSCN0633 DSCN0634 DSCN0635 DSCN0636 DSCN0643 DSCN0642 DSCN0641 DSCN0638 DSCN0637 DSCN0644 DSCN0645 DSCN0646 DSCN0649 DSCN0650 DSCN0657 DSCN0654 DSCN0653 DSCN0652 DSCN0651 DSCN0659 DSCN0660 DSCN0663 DSCN0665 DSCN0667 DSCN0674 DSCN0672 DSCN0671 DSCN0670 DSCN0668 DSCN0677 DSCN0681 DSCN0682 DSCN0683 DSCN0684

Other Projects

© 2008 -2013 Federal Construction Group - All rights reserved | Designed by iDZYNS